Competitive procedure with negotiation
Contents |
[edit] Definition
Initially introduced under the Public Contracts Regulations 2015, the competitive procedure with negotiation is one of the six main procedures for higher value regulated public sector procurement.
According to the STAR Procurement Glossary of Terms, a competitive procedure with negotiation may take place, “following the receipt of initial tender responses, [after which] the tenderer could choose to negotiate with more than one [provider] before a final contract award is made. This might be beneficial where the requirement is complex or requires innovative solutions.”
The Construction Procurement Handbook further explains that the conditions for competitive procedure with negotiation may exist when:
- The needs of the contract cannot be met without adaptation of readily available solutions.
- The supplies or services required include design or innovative solutions.
- The technical specifications of the goods or services required cannot be established precisely by the procurement officer.
- The public body has already tried to procure the goods or services using the open or restricted procedure but only received irregular or unacceptable tenders.
Guidance issued by the Office of Government Commerce (OGC) stated that this method should only be used under ‘...very exceptional circumstances’ (ref OGC: Guidance on the competitive dialogue procedure in the new procurement regulations, 2006).
[edit] Details of the procedure in Scotland
The Single Procurement Document (Scotland) - also referred to as SPD (Scotland) - is a document that contains questions used at the selection stage for post-Brexit procurement exercises in Scotland to identify suitably qualified and experienced bidders. The Supplier Journey portion of the Scottish Government’s procurement guidance website offers an overview of the competitive procedure with negotiation:
- The contract notice clearly states that this method is being used and will request the completion of an SPD (Scotland).
- Any supplier may make a request to participate.
- The supplier must submit a completed SPD within the timelines set out by the procurement officer.
- Once SPDs have been submitted and assessed, the procurement officer will prepare a shortlist of suppliers who have met the selection criteria and invite them to the initial tender phase.
- The minimum number of suppliers who can be shortlisted is three (if three meet the selection criteria requirements).
- The preparation stage can be followed by several rounds of negotiation in order for the public body to seek approved offers.
- Negotiations may result in a new or revised tender being issued.
Interested parties participating in competitive procedure with negotiation arrangements are given, on average, at least 30 days to submit selection stage documents. This timeline starts from the day the contract notice is sent for publication.
For the award stage, possible participants are also typically given a minimum of 30 days to respond. This timescale can be amended depending on whether a Prior Information Notice was issued (and how it has been used) or in instances where bids will be accepted electronically.
Details of all of the tender timelines should be provided in the tender documents. If there is a justifiable reason to change the tender closing date, the new date should be communicated to all bidders. If a tender has already been submitted, the bidder should be given the opportunity to withdraw the original bid and submit a revised one.
It is the responsibility of all suppliers to ensure that their bids have been submitted in accordance with the rules of the competition and before the specified deadline.
To respond, suppliers should:
- Register on Public Contracts Scotland (PCS).
- Formally note interest in the contract.
- Access the procurement documents available via PCS.
- Respond to the selection stage of the process.
- If successful, participate in the negotiations held.
- Access the tender documents via PCS.
- Respond to the tender, either via PCS or PCS-Tender (the procurement officers instructions will explain which system to use) to verify that the deadline can be met.
Non-conformant bids will be disqualified from the competition.
[edit] Related articles
- Competitive dialogue procedure for construction contracts.
- Contract conditions.
- Negotiated contract.
- Negotiated Procedure without Prior Publication NPwPP.
- OGC.
- OJEU procurement procedures.
- Procurement route.
- Selection criteria.
- Single Procurement Document (Scotland).
- Typical tender process for construction projects.
[edit] External resources
- Scottish Government, Construction Procurement Handbook.
- Scottish Government, Supplier Journey.
- STAR Procurement Glossary of Terms.
Featured articles and news
The context, schemes, standards, roles and relevance of the Building Safety Act.
Retrofit 25 – What's Stopping Us?
Exhibition Opens at The Building Centre.
Types of work to existing buildings
A simple circular economy wiki breakdown with further links.
A threat to the creativity that makes London special.
How can digital twins boost profitability within construction?
The smart construction dashboard, as-built data and site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure Bill
An outline of the bill with a mix of reactions on potential impacts from IHBC, CIEEM, CIC, ACE and EIC.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.